NON-CONFORMANCE Region NSW1 Saturday, 3 August 2024
NON-CONFORMANCE NSW1 Region Saturday, 3 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW03
Duration: 03/08/2024 16:25 to 03/08/2024 16:35
Amount: 72 MW
Constraint: NC-N_BW03
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 03/08/2024 10:04
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 117540
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Duration: 03/08/2024 09:01 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 2 August 2024
NON-CONFORMANCE SA1 Region Friday, 2 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/08/2024 12:10 to 02/08/2024 18:15
Amount: 14 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
RESERVE NOTICE MT PASA PUBLICATION 6 August 2024
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 117502 published on 30 July 2024.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National
Forecasting
AEMO
Cancellation - AEMO Intervention Event - SA region 01/08/2024
Cancellation - AEMO Intervention Event - SA region 01/08/2024
Refer to Market Notice 117525
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 02/08/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 117529
Direction is cancelled from: 1430 hrs 02/08/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 117526
Direction is cancelled from: 1230 hrs 02/08/2024
Manager NEM Real Time Operations
CHG0091753 | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage
Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 09/08/2024 17:00:00 AEST
Outage Start Date & Time: 08/08/2024 09:00:00 AEST
Outage End Date & Time: 09/08/2024 14:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: "The AEMO Pre-production Gas Supply Hub (GSH) environment will be refreshed (GSH databases) and system will be unavailable during the outage window.
Access to Gas Suuply Hub (GSH) Trayport interface, GSH Day Ahead auction (DAA) and Pipeline capacity trading API and GSH web portal interfaces will be unavailable.
Upon completion of the outage users will be required to log in to pre-prod Gas Supply Hub Tray-port application using their production credentials as Trayport passwords in Pre-Production environment will be replaced with their Production passwords."
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .