Market Notices

112430RECLASSIFY CONTINGENCY17/12/2023 01:35:35 AM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 17/12/2023 01:35 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
112425RECLASSIFY CONTINGENCY16/12/2023 02:49:35 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 16/12/2023 14:49

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 112405

Auto-generated on behalf of Manager NEM Real Time Operations
112413PRICES UNCHANGED16/12/2023 12:06:53 PM

[EventId:202312161135_confirmed] Prices for interval 16-Dec-2023 11:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:35.

In accordance with Market Notice 112401 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112412PRICES UNCHANGED16/12/2023 12:04:14 PM

[EventId:202312161200_confirmed] Prices for interval 16-Dec-2023 12:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 12:00.

In accordance with Market Notice 112407 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112411PRICES UNCHANGED16/12/2023 12:03:05 PM

[EventId:202312161155_confirmed] Prices for interval 16-Dec-2023 11:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:55.

In accordance with Market Notice 112406 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112410PRICES UNCHANGED16/12/2023 12:01:47 PM

[EventId:202312161150_confirmed] Prices for interval 16-Dec-2023 11:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:50.

In accordance with Market Notice 112404 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112409PRICES UNCHANGED16/12/2023 12:00:16 PM

[EventId:202312161145_confirmed] Prices for interval 16-Dec-2023 11:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:45.

In accordance with Market Notice 112403 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112408PRICES UNCHANGED16/12/2023 12:05:33 PM

[EventId:202312161140_confirmed] Prices for interval 16-Dec-2023 11:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 December 2023

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2023 11:40.

In accordance with Market Notice 112402 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112405RECLASSIFY CONTINGENCY16/12/2023 11:45:55 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 16/12/2023 11:45 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
X