117382SETTLEMENTS RESIDUE20/07/2024 01:30:31 PM

[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117286RESERVE NOTICE03/07/2024 08:10:15 PM

Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.

Manager NEM Real Time Operations
117285SETTLEMENTS RESIDUE03/07/2024 05:55:22 PM

[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Refer to market notice: 117283

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.

This is an AEMO autogenerated Market Notice.
117284RESERVE NOTICE03/07/2024 05:42:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW

Manager NEM Real Time Operations
117283SETTLEMENTS RESIDUE03/07/2024 05:30:25 PM

[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117087RESERVE NOTICE20/06/2024 07:41:48 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117086 is cancelled at 1930hrs 20/06/2024.

Manager NEM Real Time Operations
117086RESERVE NOTICE20/06/2024 06:13:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1726 MW
The minimum capacity reserve available is 1695 MW

Manager NEM Real Time Operations
117021RESERVE NOTICE15/06/2024 08:03:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.

Manager NEM Real Time Operations