112095PRICES SUBJECT TO REVIEW08/12/2023 02:55:26 PM

[EventId:202312081500_review] Prices for interval 08-Dec-2023 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 8 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112094SETTLEMENTS RESIDUE08/12/2023 02:51:32 PM

[EventId:202312081450_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 8 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1450 hrs on 8 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112093PRICES SUBJECT TO REVIEW08/12/2023 02:50:22 PM

[EventId:202312081455_review] Prices for interval 08-Dec-2023 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 8 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112092PRICES SUBJECT TO REVIEW08/12/2023 02:46:03 PM

[EventId:202312081450_review] Prices for interval 08-Dec-2023 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 8 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112090PRICES SUBJECT TO REVIEW08/12/2023 02:40:22 PM

[EventId:202312081445_review] Prices for interval 08-Dec-2023 14:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 8 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 14:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112084MARKET INTERVENTION08/12/2023 01:06:27 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 09/12/2023 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112081RESERVE NOTICE08/12/2023 01:21:12 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1180 MW.
The minimum capacity reserve available is 766 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
112076RESERVE NOTICE08/12/2023 11:52:29 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112041 has been updated at 1100 hrs 08/12/2023 to the following:

From 1530 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 776 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
112075SETTLEMENTS RESIDUE08/12/2023 11:20:28 AM

[EventId:202312081120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 11:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1120 hrs on 8 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.

Refer to market notice: 112063

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 8 December 2023.

This is an AEMO autogenerated Market Notice.