PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 23/02/2024 to 1830 hrs 23/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1342 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115009 is cancelled at 0445 hrs 23/02/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 23/02/2024 to 1800 hrs 23/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1304 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114917 is cancelled at 1400 hrs 22/02/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1251 MW.
The minimum capacity reserve available is 1076 MW.
AEMO Operations
Update to system strength constraints in North Queensland
Refer to market notice 110677
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.
A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.
The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases.
Below constraint equations in the Q-NIL set will be modified:
- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114838 is cancelled at 1430 hrs 18/02/2024.
No LOR condition is currently forecast in the STPASA period.
Manager NEM RTO
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 23/02/2024 to 1700 hrs 23/02/2024.
The forecast capacity reserve requirement is 1637 MW.
The minimum capacity reserve available is 1594 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114532 is cancelled at 1613 hrs 12/02/2024.
Manager NEM Real Time Operations