117266NON-CONFORMANCE01/07/2024 07:25:13 PM

NON-CONFORMANCE Region NSW1 Monday, 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 1 July 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: QBYNBG1, QBYNBL1
Aggregate Dispatch Group: QBYNBESS_ADG1
Duration: 01/07/2024 19:05 to 01/07/2024 19:25
Amount: -10 MW
Constraint: NC-N_QBYNBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117265NON-CONFORMANCE01/07/2024 06:35:17 PM

NON-CONFORMANCE Region NSW1 Monday, 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 1 July 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: QBYNBG1, QBYNBL1
Aggregate Dispatch Group: QBYNBESS_ADG1
Duration: 01/07/2024 18:10 to 01/07/2024 18:35
Amount: -10 MW
Constraint: NC-N_QBYNBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117264RESERVE NOTICE01/07/2024 05:34:42 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 02/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

[1.] From 0700 hrs 02/07/2024 to 0730 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 600 MW.

[2.] From 0830 hrs 02/07/2024 to 0930 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 584 MW.

[3.] From 1530 hrs 02/07/2024 to 1600 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 618 MW.


Manager NEM Real Time Operations
117263RESERVE NOTICE01/07/2024 04:48:16 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 02/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117259 is cancelled at 1645 hrs 01/07/2024

Manager NEM Real Time Operations
117262NON-CONFORMANCE01/07/2024 04:05:16 PM

NON-CONFORMANCE Region QLD1 Monday, 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 1 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 01/07/2024 15:55 to 01/07/2024 16:05
Amount: 123 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
117261NON-CONFORMANCE01/07/2024 03:30:13 PM

NON-CONFORMANCE Region NSW1 Monday, 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 1 July 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: QBYNBG1, QBYNBL1
Aggregate Dispatch Group: QBYNBESS_ADG1
Duration: 01/07/2024 14:35 to 01/07/2024 15:30
Amount: 10 MW
Constraint: NC-N_QBYNBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117260RESERVE NOTICE01/07/2024 03:54:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0800 hrs to 0830 hrs 03/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 633 MW.


AEMO Operations
117259RESERVE NOTICE01/07/2024 12:57:30 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 02/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

[1.] From 0800 hrs 02/07/2024 to 0830 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 638 MW.


Manager NEM Real Time Operations
117258MARKET SYSTEMS01/07/2024 10:32:38 AM

CHG0090790 | Completed | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090790

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm