STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0600 hrs to 0730 hrs 20/05/2024.
The forecast capacity reserve requirement is 1126 MW.
The minimum capacity reserve available is 1121 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Network Augmentation Commissioned - QLD Region - 02/05/2024
Network Augmentation Commissioned - QLD Region - 02/05/2024
Commissioned:
H13 Ross - H93 Guybal Munjan No.8917 275 kV line
Manager NEM Real Time Operations
Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024
The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024
A credible contingency event during this planned outage could cause a large reduction in generation in TAS.
Refer AEMO Network Outage Schedule (NOS) for further details.
Manager NEM Real Time Operations
SERVICE RESUMPTION- AEMO NEM Control Rooms BT Phones
SERVICE RESUMPTION - AEMO NEM Control Rooms BT Phones
Refer AEMO Electricity Market Notice 116127
AEMO advises participants that the service interruption relating to: AEMO NEM Control Rooms BT Phones has been resolved.
Participants may resume using the standard AEMO contact numbers.
Participants experiencing any further service issues should contact the AEMO Support Hub
Phone: 1300236600 Opt1
Email: supporthub@aemo.com.au
Manager NEM Real Time Operations