STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117025 has been updated at 1400 hrs 17/06/2024 to the following:
1. From 0000 hrs to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1669 MW.
2. From 0600 hrs to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1651 MW.
3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1641 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117024 has been updated at 1400 hrs 17/06/2024 to the following:
1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1692 MW.
The minimum capacity reserve available is 1565 MW.
2. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1556 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117019 has been updated at 1400 hrs 16/06/2024 to the following:
[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117018 has been updated at 1400 hrs 16/06/2024 to the following:
[1.] From 0530 hrs 19/06/2024 to 0930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1721 MW.
The minimum capacity reserve available is 1521 MW.
[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117017 is cancelled at 1400 hrs 16/06/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 21/06/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No 117008 and No 1170016 is cancelled at 1400 hrs 16/06/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116979 has been updated at 1500 hrs 15/06/2024 to the following:
[1.]From 1530 hrs 19/06/2024 to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1398 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117006 has been updated at 1500 hrs 15/06/2024 to the following:
(1.] From 0530 hrs 19/06/2024 to 1000 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1428 MW.
[2.] From 1530 hrs 19/06/2024 to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1398 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116999 has been updated at 1500 hrs 15/06/2024 to the following:
[1.] From 0630 hrs 18/06/2024 to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1696 MW.
[2.] From 1630 hrs 18/06/2024 to 0100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1687 MW.
Manager NEM Real Time Operations