121014RESERVE NOTICE27/11/2024 01:22:24 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120988 has been updated at 0100 hrs 27/11/2024 to the following:

[1.] From 1200 hrs 28/11/2024 to 2130 hrs 28/11/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 489 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
121013RESERVE NOTICE27/11/2024 01:05:51 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:

[1.] From 1700 hrs 28/11/2024 to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 728 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121012RECLASSIFY CONTINGENCY26/11/2024 09:29:20 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 26/11/2024 21:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120983

Auto-generated on behalf of Manager NEM Real Time Operations
     
121010RECLASSIFY CONTINGENCY26/11/2024 07:08:51 PM

Update - Non-credible contingency event - NSW region - 26/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 26/11/2024

Refer AEMO Electricity Market Notice 121008

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: NSW

Elements: Uranquinty Units 11,12 and 13.
Duration: 1900 hrs 26/11/2024 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
121007RESERVE NOTICE26/11/2024 04:53:53 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120972 is cancelled at 16:50 hrs 26/11/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
121005RESERVE NOTICE26/11/2024 03:44:54 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120984 is cancelled at 1545 hrs 26/11/2024.

Manager NEM Real Time Operations
     
120989RESERVE NOTICE26/11/2024 04:08:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120978 has been updated at 1500 hrs 26/11/2024 to the following:

From 0630 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1421 MW.
The minimum capacity reserve available is 1200 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120988RESERVE NOTICE26/11/2024 04:04:31 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120969 has been updated at 1500 hrs 26/11/2024 to the following:

1. From 0830 hrs to 1000 hrs 28/11/2024.
The forecast capacity reserve requirement is 1340 MW.
The minimum capacity reserve available is 1294 MW.

2. From 1030 hrs to 2300 hrs 28/11/2024.
The forecast capacity reserve requirement is 1523 MW.
The minimum capacity reserve available is 213 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120984RESERVE NOTICE26/11/2024 02:39:39 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120980 has been updated at 1435 hrs to the following:

[1.] From 1730 hrs 26/11/2024 to 1800 hrs 26/11/2024.
The forecast capacity reserve requirement is 908 MW.
The minimum capacity reserve available is 847 MW.

AEMO is seeking a market response.

AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1730 hrs on 26/11/2024.

Manager NEM Real Time Operations
     