Market Notices

119689POWER SYSTEM EVENTS31/10/2024 12:49:14 AM

Non-credible contingency event - NSW region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 31/10/2024

At 0028 hrs the Wagga B 330 kV bus tripped which offloaded the Wagga - Walla Walla SF 6Y 330 kV line and Wagga No.3 transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
119682MINIMUM SYSTEM LOAD30/10/2024 03:09:34 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 05/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 05/11/2024.

Minimum regional demand is forecast to be 1238 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1535 MW
MSL2 - 1035 MW
MSL3 - 535 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1400 hrs 05/11/2024.

AEMO Operations
     
119644MINIMUM SYSTEM LOAD29/10/2024 03:03:58 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119571 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 02/11/2024.

Minimum regional demand is forecast to be 1457 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1695 MW
MSL2 - 1195 MW
MSL3 - 695 MW


The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 02/11/2024.

AEMO Operations
     
119578MINIMUM SYSTEM LOAD28/10/2024 03:33:55 PM

Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1400 hrs 28/10/2024.

Refer to Market Notice 119497 for Forecast MSL1.


AEMO Operations
     
119571MINIMUM SYSTEM LOAD28/10/2024 03:04:41 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 02/11/2024.

Minimum regional demand is forecast to be 1491 MW at 1230 hrs, and the advisory threshold is:
MSL1 = 1695 MW
MSL2 = 1195 MW
MSL3 = 695 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1100 hrs to 1330 hrs 02/11/2024.

AEMO Operations
     
119439MINIMUM SYSTEM LOAD26/10/2024 01:18:39 PM

Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.

Refer to Market Notice 119423 for MSL1.

Manager NEM Real Time Operations
     
119423MINIMUM SYSTEM LOAD26/10/2024 09:01:24 AM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119236 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.

Minimum regional demand is forecast to be 1302 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1000 hrs to 1400 hrs 26/10/2024.

AEMO Operations
     
119412MINIMUM SYSTEM LOAD25/10/2024 02:56:16 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119315 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.

Minimum regional demand is forecast to be 1732 MW at 1230 hrs, and the advisory threshold is:
MSL1 = 1795 MW
MSL2 = 1295 MW
MSL3 = 795 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 26/10/2024.

AEMO Operations
     
119315MINIMUM SYSTEM LOAD24/10/2024 02:52:43 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.

Minimum regional demand is forecast to be 1648 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1860 MW
MSL2 - 1360 MW
MSL3 - 860 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 27/10/2024.

AEMO Operations
     