Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120679
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120673 is cancelled at 1400 hrs 20/11/2024
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 0530 hrs to 0800 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1164 MW.
2. From 0830 hrs to 2300 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120674 has been updated at 1400 hrs 20/11/2024 to the following:
1. From 1130 hrs to 1400 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 889 MW.
2. From 2030 hrs to 2300 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120676 has been updated at 1400 hrs 20/11/2024 to the following:
1. From 1300 hrs to 1530 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 782 MW.
AEMO Operations
[EventId:202411201400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 November 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 20 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.
Refer to market notice: 120709
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 20 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411201240_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 November 2024 12:40
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 20 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1240 hrs on 20 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411192040_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 November 2024 20:40
Issued by Australian Energy Market Operator Ltd at 2040 hrs on 19 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Refer to market notice: 120687
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2040 hrs on 19 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411191800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 November 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 19 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1800 hrs on 19 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.