Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.120112 is cancelled at 2010 hrs 07/11/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.120113 is cancelled at 1945 hrs 07/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1201 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1090 MW
The minimum capacity reserve available is 897 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 14:35 to 07/11/2024 15:05
Amount: -32 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119882 is cancelled at 1900 hrs 04/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW
Manager NEM Real Time Operations
CHG0099569 | Production | Maintenance on Gas B2B Hub databases
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .