PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1430 hrs 28/11/2024 to 1500 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1226 MW.
[2.] From 1600 hrs 28/11/2024 to 1700 hrs 28/11/2024.
The forecast capacity reserve requirement is 1576 MW.
The minimum capacity reserve available is 1147 MW.
[3.] From 1900 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1154 MW.
Manager NEM Real Time Operations
Direction - NSW region to Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS
Direction - NSW region to Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS
Refer to Market Notice 121070.
In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Iberdrola Australia Wallgrove Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS at 1330 hrs 27/11/2024
Type of resource: bi-directional unit
Required actions: Maintain 59 MWh Energy Storage Level and follow dispatch targets at 1430 hrs 27/11/2024
Services provided: Reserve
Circumstances necessitating the Direction: Reliability
Circumstances necessitating the Direction additional detail: intervention is required to maintain the reliability standard
Expected duration: 1900 hrs 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1500 hrs 28/11/2024 to 1600 hrs 28/11/2024.
The forecast capacity reserve requirement is 1176 MW.
The minimum capacity reserve available is 1026 MW.
[2.] From 1700 hrs 28/11/2024 to 1900 hrs 28/11/2024.
The forecast capacity reserve requirement is 1121 MW.
The minimum capacity reserve available is 351 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1700 hrs 28/11/2024 to 1730 hrs 28/11/2024.
The forecast capacity reserve requirement is 1248 MW.
The minimum capacity reserve available is 801 MW.
[2.] From 1830 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1264 MW.
The minimum capacity reserve available is 887 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 28/11/2024 to 1830 hrs 28/11/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 351 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121023 has been updated at 1200 hrs 27/11/2024 to the following:
1. From 1500 hrs to 1630 hrs 28/11/2024.
The forecast capacity reserve requirement is 1129 MW.
The minimum capacity reserve available is 1025 MW.
2. From 1730 hrs to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 1083 MW.
The minimum capacity reserve available is 1010 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 28/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121049 has been updated at 1130 hrs to the following:
[1.] From 1430 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 5 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1330 hrs on 27/11/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 27/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121053 is cancelled at 1100 hrs 27/11/2024.
Manager NEM Real Time Operations