Filter by category
Filter by Date
Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024
Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024
A planned outage of Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line in the NSW region was scheduled to be completed at 1700 hrs 05/11/2024
The outage has been completed by 0840 hrs 05/11/2024.
Constraint set(s) invoked:
N-MUTW_88
N-TWUL_85
N-TW_SVC
N-DM_SVC
N-X_TW_330_BUS3-5
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load 2 (MSL2) in the VIC Region on 10/11/2024
Cancellation - Forecast MSL2, VIC Region at 0700 hrs 05/11/2024.
Refer to Market Notice 119852 for Forecast MSL2.
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1735 MW
- MSL2 - 1235 MW
- MSL3 - 735 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 0930 hrs to 1230 hrs 10/11/2024. Minimum regional demand is forecast to be 1262 MW at 1230 hrs.
2. From 1300 hrs to 1500 hrs 10/11/2024. Minimum regional demand is forecast to be 1249 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 09/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 09/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1745 MW
- MSL2 - 1245 MW
- MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1100 hrs to 1400 hrs 09/11/2024. Minimum regional demand is forecast to be 1488 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations
NEM Local Temperature Alerts for QLD from 04 Nov 2024 to 08 Nov 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 5th Nov, 7th Nov, 8th Nov
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Forecast Minimum System Load MSL2 condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 = 1760 MW
- MSL2 = 1260 MW
- MSL3 = 760 MW
The regional demand is forecast to be below the MSL2 threshold for the following period:
From 1230 hrs 10/11/2024 to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1236 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.
AEMO is seeking a market response.
AEMO Operations
Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024
Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024
At 1330 hrs 03/11/2024 there will be a short notice outage of all three poles of Directlink.
The following constraint set(s) to be invoked at 1330 hrs 03/11/2024
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region 03/11/2024.
Cancellation - MSL1- VIC Region at 1330 hrs 03/11/2024.
Refer to Market Notice 119760 for MSL1.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1770 MW
o MSL2 - 1270 MW
o MSL3 - 770 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1100 hrs to 1400 hrs 03/11/2024. Minimum regional demand is forecast to be 1424 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations