Market Notices

121764RESERVE NOTICE12/12/2024 09:08:38 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs to 1900 hrs 13/12/2024.
The forecast capacity reserve requirement is 1182 MW.
The minimum capacity reserve available is 922 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121762RESERVE NOTICE12/12/2024 09:05:57 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121735 has been updated at 0800 hrs 12/12/2024 to the following:

1. From 1400 hrs to 1500 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 239 MW.

2. From 1930 hrs to 2100 hrs 16/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 136 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121761RESERVE NOTICE12/12/2024 08:51:13 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1930 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1075 MW.


Manager NEM Real Time Operations
     
121760RESERVE NOTICE12/12/2024 09:04:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:

From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121759RECALL GEN CAPACITY12/12/2024 09:09:42 AM

Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.

Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121757RECALL GEN CAPACITY12/12/2024 09:07:27 AM

Request for Generator Recall Information for the period 16/12/2024 for Region VIC

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121767.

Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
121756RESERVE NOTICE12/12/2024 07:50:25 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.


Manager NEM Real Time Operations
     
121752RESERVE NOTICE12/12/2024 04:25:47 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.


Manager NEM Real Time Operations
     
121736RESERVE NOTICE12/12/2024 12:55:44 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 578 MW.
The minimum capacity reserve available is 207 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm