121415SETTLEMENTS RESIDUE03/12/2024 11:45:24 AM

[EventId:202412031145_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 December 2024 11:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 3 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1145 hrs on 3 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121409GENERAL NOTICE03/12/2024 10:22:45 AM

NEM Local Temperature Alerts for SA from 03 Dec 2024 to 07 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 5th Dec, 6th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
121387RESERVE NOTICE02/12/2024 07:22:04 PM

Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.

Manager NEM Real Time Operations
     
121384RESERVE NOTICE02/12/2024 05:16:49 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1066 MW

Manager NEM Real Time Operations
     
121375SETTLEMENTS RESIDUE02/12/2024 01:30:29 PM

[EventId:202412021330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 December 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 2 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.

Refer to market notice: 121358

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 2 December 2024.

This is an AEMO autogenerated Market Notice.
     
121358SETTLEMENTS RESIDUE02/12/2024 11:05:43 AM

[EventId:202412021105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 December 2024 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 2 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 2 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121357GENERAL NOTICE02/12/2024 10:41:14 AM

NEM Local Temperature Alerts for SA from 02 Dec 2024 to 06 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 5th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning


     
121285MARKET INTERVENTION30/11/2024 09:30:31 AM

Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024

Refer Market Notice 121281

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0915 hrs 30/11/2024.

Manager NEM Real Time Operations
     
121281MARKET INTERVENTION30/11/2024 08:19:02 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 121280

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 0900 hrs 30/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     