Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all three legs of Directlink .
The following constraint set was invoked at 1440 hrs 16/02/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Moorabool Sydenham 500 kV lines - Vic region - 15/02/2024
At 1905 hrs 15/02/2024 in the Victoria region interim work was completed at Moorabool and Sydenham terminal stations to provide additional 500 kV bus ties.
As a result of this completed work the South Australia region is no longer on a credible risk of separation.
Constraint set changes.
Invoked:
V-X_MLSY_MLTS_TIE
Revoked:
F-V-X_ML_BUSTIE_500
I-VS_050
S-X_BC_CP
V-X_MLSY
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Rfer Market Notices 114577, 114768, 114686
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
INC0126874 | RESOLVED | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - RESOLVED
The issue with the standing data updates not reflecting in MSATS Enterprise MDM has been resolved.
There are no further steps to be completed. The service is now fully restored, and no further communication will be released unless there is a change of status.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
CHG0082504 | Completed | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0235 hrs 14/02/2024
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations
Inter-regional transfer limit variation: South Morang - Sydenham No 1 and 2 500 kV lines (VIC) - Voltage Control
The South Morang - Sydenham No 1 and 2 500 kV lines have been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0105 hrs 14/02/2024
V-SMSY
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - VIC region - 13/02/2024 -
Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - 13/02/2024
At 1308 hrs 13/02/2024 the Moorabool - Sydenham No1 and No2 500 kV lines tripped.
Refer Market notices 114577 and 114625.
The following constraint set(s) are invoked :
V-X_MLSY
F-V-X_ML_BUSTIE_500
I-VS_050
These constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Refer to the Network outage scheduler (NOS) for more details:
Manager NEM Real Time Operations
CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .