Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 120356
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 14/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 13/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 13/11/2024 15:04
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 120338
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120321
Direction is cancelled from: 1630 hrs 13/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120321
Direction is cancelled from: 1800 hrs 13/11/2024
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 14/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 15/11/2024
Network Augmentation Commissioned - QLD Region - 15/11/2024
Commissioned:
S2 Halys - H148 Diamondy 8996 275 kV line
Manager NEM Real Time Operations
[EventId:202411131320_confirmed] Prices for interval 13-Nov-2024 13:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:20.
In accordance with Market Notice 120344 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411131340_confirmed] Prices for interval 13-Nov-2024 13:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:40.
In accordance with Market Notice 120348 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411131335_confirmed] Prices for interval 13-Nov-2024 13:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:35.
In accordance with Market Notice 120347 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.