120360MARKET INTERVENTION13/11/2024 03:08:00 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 120356

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 14/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 13/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
120359RECLASSIFY CONTINGENCY13/11/2024 03:04:11 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 13/11/2024 15:04

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120338

Auto-generated on behalf of Manager NEM Real Time Operations
     
120358MARKET INTERVENTION13/11/2024 04:38:53 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120321

Direction is cancelled from: 1630 hrs 13/11/2024

Manager NEM Real Time Operations
     
120357MARKET INTERVENTION13/11/2024 05:44:14 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 120321

Direction is cancelled from: 1800 hrs 13/11/2024

Manager NEM Real Time Operations
     
120356MARKET INTERVENTION13/11/2024 02:17:40 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 14/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
120355GENERAL NOTICE15/11/2024 05:06:59 PM

Network Augmentation Commissioned - QLD Region - 15/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 15/11/2024

Commissioned:
S2 Halys - H148 Diamondy 8996 275 kV line

Manager NEM Real Time Operations
     
120354PRICES UNCHANGED13/11/2024 01:46:08 PM

[EventId:202411131320_confirmed] Prices for interval 13-Nov-2024 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:20.

In accordance with Market Notice 120344 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120353PRICES UNCHANGED13/11/2024 01:44:56 PM

[EventId:202411131340_confirmed] Prices for interval 13-Nov-2024 13:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:40.

In accordance with Market Notice 120348 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120352PRICES UNCHANGED13/11/2024 01:43:52 PM

[EventId:202411131335_confirmed] Prices for interval 13-Nov-2024 13:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 13:35.

In accordance with Market Notice 120347 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     