Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Sunday, 7 January 2024
NON-CONFORMANCE VIC1 Region Sunday, 7 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS1
Duration: 07/01/2024 00:55 to 07/01/2024 01:05
Amount: -23 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 4 January 2024
NON-CONFORMANCE QLD1 Region Thursday, 4 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BARCALDN
Duration: 04/01/2024 04:30 to 04/01/2024 04:45
Amount: 9 MW
Constraint: NC-Q_BARCALDN
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for VIC from 02 Jan 2024 to 06 Jan 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
VIC
Mildura Ap (39+ Deg C): 2nd Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update - Lightning vulnerable equipment in QLD region
Update - Lightning vulnerable equipment in QLD region
Special Reclassification of Transmission Equipment during lightning
Refer to AEMO Electricity Market Notice 112581 and 112884.
At 1424 hrs 21/12/2023, the Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No. 3 275/110 kV transformers
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers to be vulnerable due to lightning.
Manager NEM Real Time Operations
Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023
Cancellation - MSL1 - VIC Region
Refer Market Notice 112936
The MSL1 condition for 31/12/2023 is cancelled at 1600 hrs 31/12/2023
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 31 December 2023
NON-CONFORMANCE VIC1 Region Sunday, 31 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNSF1
Duration: 31/12/2023 10:25 to 31/12/2023 10:45
Amount: 25 MW
Constraint: NC-V_GANNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 31/12/2023 to 1400 hrs 31/12/2023.
Minimum scheduled demand is forecast to be 1300 MW at 1300 hrs and the secure threshold for the forecast operating conditions is 2,000 MW.
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled generation, curtailment of non-scheduled generation, and/or a direction to increase operational demand.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 30 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 30 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF2
Duration: 30/12/2023 12:50 to 30/12/2023 13:05
Amount: 163 MW
Constraint: NC-N_NEWENSF2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 27 December 2023
NON-CONFORMANCE NSW1 Region Wednesday, 27 December 2023
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 27/12/2023 14:35 to 27/12/2023 14:45
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations