STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114378 s cancelled at 1400 hrs 08/02/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
NEM Local Temperature Alerts for SA from 08 Feb 2024 to 12 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
QNI Minor testing (NSW to Qld) 7th February 2024
Refer to market notice 113265
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Wednesday 7th February 2024 from 1400 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 06/02/2024 to 1930 hrs 06/02/2024.
The forecast capacity reserve requirement is 1179 MW.
The minimum capacity reserve available is 988 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114379 is cancelled at 1715 hrs 06/02/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114359 has been updated at 1615 hrs to the following:
[1.] From 1830 hrs 06/02/2024 to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 1128 MW.
The minimum capacity reserve available is 1095 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1800 hrs 13/02/2024.
The forecast capacity reserve requirement is 1515 MW.
The minimum capacity reserve available is 1478 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114357 has been updated at 1110 hrs to the following:
[1.] From 1730 hrs 06/02/2024 to 2030 hrs 06/02/2024.
The forecast capacity reserve requirement is 1014 MW.
The minimum capacity reserve available is 884 MW.
Manager NEM Real Time Operations
Fast Frequency Response Market - Increase in L1 FCAS dispatch cap from 12 February 2024.
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 12 Febraury AEMO will:
Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 100 MW to 125 MW
Retain the cap on dispatch of Very Fast Raise (R1) Contingency FCAS at 225 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.