STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113465 has been updated at 0900 hrs 19/01/2024 to the following:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 563 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 720 MW.
The minimum capacity reserve available is 708 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113346 is cancelled at 0900 hrs 17/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1530 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 696 MW.
The minimum capacity reserve available is 677 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113337 is cancelled at 0430 hrs 17/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1500 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 708 MW.
The minimum capacity reserve available is 671 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113285 is cancelled at 0700 hrs 16/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 26/12/2023
Non-credible contingency event - QLD region - 26/12/2023
At 2345 hrs the Strathmore Clare South 7208 and the Strathmore Clare South Tee King Creek 7128 132kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations