STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113556 has been updated at 1400 hrs 22/01/2024 to the following:
From 1730 hrs to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113555 has been updated at 1400 hrs 22/01/2024 to the following:
From 1430 hrs to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 843 MW
AEMO Operations
CHG0082504:MSATS - Business to Business data exchange
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202401221430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 22 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.
Refer to market notice: 113600
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 22 January 2024.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 1029 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1244 MW.
The minimum capacity reserve available is 1180 MW.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 22/01/2024 to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 631 MW.
The minimum capacity reserve available is 583 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1430 hrs on 22/01/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113582 has been updated at 1100 hrs to the following:
[1.] From 1830 hrs 22/01/2024 to 2000 hrs 22/01/2024.
The forecast capacity reserve requirement is 1100 MW.
The minimum capacity reserve available is 690 MW.
Manager NEM Real Time Operations
[EventId:202401221100_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 22 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1100 hrs on 22 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.