Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119882 is cancelled at 1900 hrs 04/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1735 MW
- MSL2 - 1235 MW
- MSL3 - 735 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 0930 hrs to 1230 hrs 10/11/2024. Minimum regional demand is forecast to be 1262 MW at 1230 hrs.
2. From 1300 hrs to 1500 hrs 10/11/2024. Minimum regional demand is forecast to be 1249 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 09/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 09/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1745 MW
- MSL2 - 1245 MW
- MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1100 hrs to 1400 hrs 09/11/2024. Minimum regional demand is forecast to be 1488 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations
Forecast Minimum System Load MSL2 condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 = 1760 MW
- MSL2 = 1260 MW
- MSL3 = 760 MW
The regional demand is forecast to be below the MSL2 threshold for the following period:
From 1230 hrs 10/11/2024 to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1236 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.
AEMO is seeking a market response.
AEMO Operations
CHG0099569 | Production | Maintenance on Gas B2B Hub databases
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation - MSL1- VIC Region 03/11/2024.
Cancellation - MSL1- VIC Region at 1330 hrs 03/11/2024.
Refer to Market Notice 119760 for MSL1.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1770 MW
o MSL2 - 1270 MW
o MSL3 - 770 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1100 hrs to 1400 hrs 03/11/2024. Minimum regional demand is forecast to be 1424 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region on 02/11/2024
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region at 1200 hrs 02/11/2024.
Refer to Market Notice 119742.