Market Notices

120465RESERVE NOTICE14/11/2024 08:40:46 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1630 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The forecast capacity reserve requirement is 1221 MW.
The minimum capacity reserve available is 1163 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120413GENERAL NOTICE14/11/2024 10:21:41 AM

NEM Local Temperature Alerts for SA from 14 Nov 2024 to 18 Nov 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 16th Nov

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
120355GENERAL NOTICE15/11/2024 05:06:59 PM

Network Augmentation Commissioned - QLD Region - 15/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 15/11/2024

Commissioned:
S2 Halys - H148 Diamondy 8996 275 kV line

Manager NEM Real Time Operations
     
120307GENERAL NOTICE12/11/2024 11:48:51 AM

Project Energy Connect (PEC-1) testing 12th November 2024 1630-2200 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120276

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 16:30hrs to 22:00hrs

This test includes switching of a transmission line in SA and switching of a reactive plant in NSW.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120276GENERAL NOTICE11/11/2024 05:07:24 PM

Project Energy Connect (PEC-1) testing 12th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120016

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 06:00hrs to 11:00hrs

This test includes the synchronization of the new PEC Stage 1 interconnector and testing of the Phase Shifting transformer at Buronga substation.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120253INTER-REGIONAL TRANSFER11/11/2024 01:31:43 PM

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.

The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV

This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120126RESERVE NOTICE07/11/2024 11:49:27 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120120 is cancelled at 2345 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120120RESERVE NOTICE07/11/2024 09:23:02 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 727 MW.
The minimum capacity reserve available is 694 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120117RESERVE NOTICE07/11/2024 08:13:20 PM

Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.120112 is cancelled at 2010 hrs 07/11/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm