Filter by category
Filter by Date
Direction - VIC region to Snowy Hydro Limited - MURR2-2 MURRAY2
Direction - VIC region to Snowy Hydro Limited - MURR2-2 MURRAY2
Refer to Market Notice 120404
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Snowy Hydro Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2 at 0630 hrs 15/11/2024
Type of resource: generating unit operating as synchronous condenser
Required actions: Remain synchronised and operate as a synchronous condenser at 0630 hrs 15/11/2024
Services provided: System Strength
Circumstances necessitating the Direction:System Strength
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0900 hrs 15/11/2024.
Snowy Hydro Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120468
The JLB02 JEERALANG B PO direction is now expected to stay in place until 0700 hrs 15/11/2024.
The direction update is issued at 0415 hrs 15/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120467
The JLB01 JEERALANG B PO direction is now expected to stay in place until 0700 hrs 15/11/2024.
The direction update is issued at 0415 hrs 15/11/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 15 November 2024
NON-CONFORMANCE QLD1 Region Friday, 15 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 15/11/2024 00:30 to 15/11/2024 00:55
Amount: -38 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120464
The JLB02 JEERALANG B PO direction is now expected to stay in place until 0500 hrs 15/11/2024.
The direction update is issued at 2140 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120463
The JLB01 JEERALANG B PO direction is now expected to stay in place until 0500 hrs 15/11/2024.
The direction update is issued at 2140 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120443
The JLB02 JEERALANG B PO direction is now expected to stay in place until 2300 hrs 14/11/2024.
The direction update is issued at 2015 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120442
The JLB01 JEERALANG B PO direction is now expected to stay in place until 2300 hrs 14/11/2024.
The direction update is issued at 2015 hrs 14/11/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024
NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 14/11/2024 17:50 to 14/11/2024 18:15
Amount: 23 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations