Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024
Refer to market notice 119963
The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.
Terry Liu
AEMO Operations
Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119961
This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.
The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Mya San
AEMO Operations
Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119901
The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.
The test is for flows in both directions up to 50 MW.
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Terry Liu
AEMO Operations
Project Energy Connect (PEC-1) testing 6th November 2024 for flows in both directions
Refer to market notice 118945
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 6th November from 07:00hrs to 11:00hrs
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
NEM Local Temperature Alerts for QLD, SA from 05 Nov 2024 to 09 Nov 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 5th Nov, 6th Nov, 7th Nov, 8th Nov, 9th Nov
SA
Port Augusta Ap (39+ Deg C): 5th Nov
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NEM Local Temperature Alerts for QLD from 04 Nov 2024 to 08 Nov 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 5th Nov, 7th Nov, 8th Nov
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
CHG0099569 | Production | Maintenance on Gas B2B Hub databases
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.
Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1
Manager NEM Real Time Operations