120678MARKET SYSTEMS19/11/2024 03:35:12 PM

INC0138395 - P1 - Electricity Market Management System service- RESOLVED

AEMO ELECTRICITY MARKET NOTICE

This incident has been uplifted to a P1.

The service interruption relating to the Electricity Market Management System service has been resolved.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
120671RESERVE NOTICE19/11/2024 03:33:39 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1600 hrs to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 199 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120662SETTLEMENTS RESIDUE19/11/2024 02:30:21 PM

[EventId:202411191400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 November 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1423 hrs on 19 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.

Refer to market notice: 120655

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 19 November 2024.

This is an AEMO autogenerated Market Notice.
     
120661MARKET SYSTEMS19/11/2024 02:29:10 PM

INC0138395 - Electricity Market Management System service- RESOLVED

AEMO ELECTRICITY MARKET NOTICE

The service interruption relating to the Electricity Market Management System service has been resolved.

For further enquiries please contact the AEMO Support Hub

Phone: 1300 236 600

Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
120655SETTLEMENTS RESIDUE19/11/2024 12:20:32 PM

[EventId:202411191220_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 November 2024 12:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1220 hrs on 19 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120640SETTLEMENTS RESIDUE18/11/2024 09:01:50 PM

[EventId:202411182100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 November 2024 21:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2100 hrs on 18 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 November 2024.

Refer to market notice: 120620

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2100 hrs on 18 November 2024.

This is an AEMO autogenerated Market Notice.
     
120636MARKET INTERVENTION18/11/2024 06:24:54 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120609

Direction is cancelled from: 1830 hrs 18/11/2024

Manager NEM Real Time Operations
     
120626MARKET INTERVENTION18/11/2024 04:33:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120553

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.

The direction update is issued at 1630 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120625MARKET INTERVENTION18/11/2024 04:37:54 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1630 hrs 18/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 19/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     