Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 29/11/2024 13:20 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Duration: 29/11/2024 13:16 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411290710_review] Prices for interval 29-Nov-2024 07:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411290705_review] Prices for interval 29-Nov-2024 07:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411290700_review] Prices for interval 29-Nov-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411290655_review] Prices for interval 29-Nov-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411290650_review] Prices for interval 29-Nov-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411290645_review] Prices for interval 29-Nov-2024 06:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0640 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 28/11/2024 19:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 121145