Reclassification of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton No.1 and No.2 110kV lines in TAS due to bushfire.
Reclassification of a non-credible contingency event as a credible contingency event due to bushfire.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS
Lines: Burnie - Port Latta - Smithton No.1 and No.2 110kV lines
Duration: 27/02/2024 14:00 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 27/02/2024 13:30 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202402271330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 February 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 February 2024.
Refer to market notice: 115207
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 27 February 2024.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115203 has been updated at 1200 hrs 27/02/2024 to the following:
From 1730 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 771 MW.
The minimum capacity reserve available is 578 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202402271205_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 February 2024 12:05
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 27 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1205 hrs on 27 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/02/2024
Refer Market Notice 115151
The AEMO Intervention Event and all associated directions are cancelled from 1130 hrs 27/02/2024
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115201 has been updated at 1000 hrs 27/02/2024 to the following:
From 1430 hrs 29/02/2024 to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1341 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 336 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0085747 | UPDATED | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Change Start Date & Time: 04/03/2024 08:00:00 AEST
Change End Date & Time: 08/03/2024 19:00:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailble between 4th March until cob 8th March 2024.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .