112559GENERAL NOTICE21/12/2023 09:53:10 AM

QNI Minor testing (NSW to Qld) 21st December 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 112396

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Thursday 21st December from 1400 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
112396GENERAL NOTICE16/12/2023 09:14:41 AM

QNI Minor testing (NSW to Qld) 16th December 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 110640

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Tuesday 16th December from 0930 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
112373GENERAL NOTICE15/12/2023 10:10:57 AM

Network Augmentation Commissioned - SA Region - 15/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 15/12/2023

Commissioned:
Bundey 330kV substation, 330kV East Bus and 330kV West Bus.

Manager NEM Real Time Operations
112361GENERAL NOTICE14/12/2023 07:47:56 PM

Network Augmentation Commissioned - QLD Region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 14/12/2023

Commissioned:
R15 MacIntyre 330 kV Switching Station
R14 Tummaville - R15 MacIntyre No.9918 330 kV Line
R14 Tummaville - R15 MacIntyre No.9919 330 kV Line

Manager NEM Real Time Operations
112320GENERAL NOTICE14/12/2023 02:04:02 PM

Update - Vulnerbale lines - SA region

AEMO ELECTRICITY MARKET NOTICE.

Vulnerable lines in SA region.

[Special Reclassification of Transmission Lines during lightning]


Refer to AEMO Electricity Market Notices 111818


At 1350 28/11/2023 hrs Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers were reclassified due to the elements tripping at 0534 hrs 28/11/2023

The cause of trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the following elements to be vulnerable due to lightning.


Elements: Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers.


Manager NEM Real Time Operations
112301GENERAL NOTICE14/12/2023 10:57:26 AM

NEM Local Temperature Alerts for VIC from 14 Dec 2023 to 18 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

VIC
Mildura Ap (39+ Deg C): 18th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112262GENERAL NOTICE13/12/2023 05:42:21 PM

Update - Vulnerable lines in TAS region.

AEMO ELECTRICITY MARKET NOTICE.

Vulnerable lines in TAS region.

Refer to AEMO Electricity Market Notice 112248.

At 1324 hrs 13/12/2023 the Hadspen - Palmerston No.3 & No.4 110 kV lines tripped and auto reclosed.

The cause of trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the Hadspen - Palmerston No.3 & No.4 110 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
112249MARKET SYSTEMS13/12/2023 02:02:59 PM

CHG0082097 | Completed | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112247POWER SYSTEM EVENTS13/12/2023 01:43:17 PM

Non-credible contingency event - TAS region - 13/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 13/12/2023

At 1324 hrs the Hadspen - Palmerston No.3 & No.4 110 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.