Market Notices

114540NON-CONFORMANCE12/02/2024 08:25:15 PM

NON-CONFORMANCE Region QLD1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 12 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 12/02/2024 20:15 to 12/02/2024 20:25
Amount: -63 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
114529NON-CONFORMANCE12/02/2024 01:40:10 PM

NON-CONFORMANCE Region VIC1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 12 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: BALBG1, BALBL1
Aggregate Dispatch Group: BALBESS_ADG1
Duration: 12/02/2024 13:30 to 12/02/2024 13:40
Amount: 23 MW
Constraint: NC-V_BALBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114523NON-CONFORMANCE12/02/2024 11:41:06 AM

NON-CONFORMANCE Region NSW1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 12 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 50 MW
Constraint: NC-N_RESS2_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114522NON-CONFORMANCE12/02/2024 11:40:16 AM

NON-CONFORMANCE Region NSW1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 12 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114466NON-CONFORMANCE10/02/2024 10:55:13 AM

NON-CONFORMANCE Region VIC1 Saturday, 10 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 10 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNSF1
Duration: 10/02/2024 10:40 to 10/02/2024 10:55
Amount: 25 MW
Constraint: NC-V_GANNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114459MARKET SYSTEMS09/02/2024 03:04:19 PM

CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0083624
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub

Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114421NON-CONFORMANCE07/02/2024 03:50:18 PM

NON-CONFORMANCE Region QLD1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 07/02/2024 15:40 to 07/02/2024 15:50
Amount: -37 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114416NON-CONFORMANCE07/02/2024 02:05:15 PM

NON-CONFORMANCE Region VIC1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GLRWNSF1
Duration: 07/02/2024 14:00 to 07/02/2024 14:05
Amount: 103 MW
Constraint: NC-V_GLRWNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114375MARKET SYSTEMS06/02/2024 02:01:20 PM

CHG0082609 | Production | MSATS-CATS Production Maintenance

Change Number: CHG0082609
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time: 18/02/2024 10:00:00 AEST
Outage End Date & Time: 18/02/2024 14:00:00 AEST

Environment: Production

The change has some login outages that are below and will impact participants logging into the web portal for MSATS, OPDMS, NOS and EMMS production environments.
AEMO recommends users who need to use these AEMO services, login prior to the start of the outage and remain logged in.
NOTE: If you log out of this session, you will be unable to log back in until the completion of the outage.
A URM outage will occur between 11:00 - 11:30 AEST and have an expected outage duration of upto 15 minutes. During this time users will not be able to have new login sessions into TMM, OPDMS, NOS or EMMS WebPortal.

The MSATS outage is 10:00 - 14:00 AEST which is the agreed maintenance window.
Participants should be aware that: MSATS, Meter data processing, RM reports, B2B, B2M screen, NMI Discovery, CDR, CDP will not be available Participant passwords will be retained. Users that log out and users that try to log in once the URM outage has commenced will only be able to log in after URM outage is complete. Any password resets or new account creations completed during the URM outage window will need to be redone MSATS FTP sessions will be disabled during outage Wholesale MMS FTP will still be available .

The redirection menu will be unavailable during the MSATS outage timeframe Report any impacts to the AEMO Information and Support Hub or call 1300 236 648.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm