Filter by category
Filter by Date
CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region VIC1 Sunday, 7 January 2024
NON-CONFORMANCE VIC1 Region Sunday, 7 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS1
Duration: 07/01/2024 00:55 to 07/01/2024 01:05
Amount: -23 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0082511 | Pre-Production | Pre-Prod MSATS 50.0.4 LCCD Defect Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 09/01/2024 13:00:00 AEST
Change End Date & Time: 09/01/2024 17:00:00 AEST
Outage Start Date & Time: 09/01/2024 13:00:00 AEST
Outage End Date & Time: 09/01/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region QLD1 Thursday, 4 January 2024
NON-CONFORMANCE QLD1 Region Thursday, 4 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BARCALDN
Duration: 04/01/2024 04:30 to 04/01/2024 04:45
Amount: 9 MW
Constraint: NC-Q_BARCALDN
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region VIC1 Sunday, 31 December 2023
NON-CONFORMANCE VIC1 Region Sunday, 31 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNSF1
Duration: 31/12/2023 10:25 to 31/12/2023 10:45
Amount: 25 MW
Constraint: NC-V_GANNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 30 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 30 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF2
Duration: 30/12/2023 12:50 to 30/12/2023 13:05
Amount: 163 MW
Constraint: NC-N_NEWENSF2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 27 December 2023
NON-CONFORMANCE NSW1 Region Wednesday, 27 December 2023
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 27/12/2023 14:35 to 27/12/2023 14:45
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 22 December 2023
NON-CONFORMANCE QLD1 Region Friday, 22 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 22/12/2023 15:30 to 22/12/2023 15:35
Amount: 10 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations