Filter by category
Filter by Date
[EventId:202407300755_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 30 July 2024 07:55
Issued by Australian Energy Market Operator Ltd at 0755 hrs on 30 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 30 July 2024.
Refer to market notice: 117505
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 0755 hrs on 30 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407300730_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 30 July 2024 07:30
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 30 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 30 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 0730 hrs on 30 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - VIC Region - 30/07/2024
Network Augmentation Commissioned - VIC Region - 30/07/2024
Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:
Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line
Manager NEM Real Time Operations
[EventId:202407251115_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 July 2024 11:15
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 25 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Refer to market notice: 117439
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1115 hrs on 25 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407251000_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 July 2024 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 25 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1000 hrs on 25 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202407201430_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 20 July 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 20 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.
Refer to market notice: 117382
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1430 hrs on 20 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - VIC Region - 18/07/2024
Network Augmentation Commissioned - VIC Region - 18/07/2024
At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:
Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations