115657MARKET INTERVENTION16/03/2024 02:26:08 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115655

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 17/03/2024 will be inadequate to maintain a secure operating state in SA.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 16/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115656NON-CONFORMANCE16/03/2024 09:05:19 AM

NON-CONFORMANCE Region NSW1 Saturday, 16 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 16 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 16/03/2024 09:00 to 16/03/2024 09:05
Amount: 15 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
115655MARKET INTERVENTION15/03/2024 05:21:21 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 17/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115654SETTLEMENTS RESIDUE15/03/2024 04:00:21 PM

[EventId:202403151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Refer to market notice: 115646

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 March 2024.

This is an AEMO autogenerated Market Notice.
115653NON-CONFORMANCE15/03/2024 03:40:17 PM

NON-CONFORMANCE Region QLD1 Friday, 15 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 15 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 15/03/2024 15:20 to 15/03/2024 15:40
Amount: -16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
115652INTER-REGIONAL TRANSFER15/03/2024 02:52:51 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 1445 hrs 15/03/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115651MARKET INTERVENTION15/03/2024 04:27:07 PM

Update - Direction - SA Region - 13/03/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 13/03/2024

Refer Market Notice 115613

The AEMO intervention event that commenced from interval ending 1705 hrs on 13/03/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
115647MARKET SYSTEMS15/03/2024 02:27:56 PM

CHG0086078 | Production | EMMS Production Bay transfer

Change Number: CHG0086078
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 18/03/2024 08:00:00 AEST
Change End Date & Time: 20/03/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: EMMS Bay transfer is scheduled for 19th March is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
115646SETTLEMENTS RESIDUE15/03/2024 02:10:29 PM

[EventId:202403151410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 14:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 15 March 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 15 March 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.