Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 115655
The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 17/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 16/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 16 March 2024
NON-CONFORMANCE NSW1 Region Saturday, 16 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 16/03/2024 09:00 to 16/03/2024 09:05
Amount: 15 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 17/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202403151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 March 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Refer to market notice: 115646
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 March 2024.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Friday, 15 March 2024
NON-CONFORMANCE QLD1 Region Friday, 15 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 15/03/2024 15:20 to 15/03/2024 15:40
Amount: -16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of the Murraylink interconnector.
The following constraint set was invoked at 1445 hrs 15/03/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Update - Direction - SA Region - 13/03/2024
Update - Direction - SA Region - 13/03/2024
Refer Market Notice 115613
The AEMO intervention event that commenced from interval ending 1705 hrs on 13/03/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
CHG0086078 | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 18/03/2024 08:00:00 AEST
Change End Date & Time: 20/03/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: EMMS Bay transfer is scheduled for 19th March is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
[EventId:202403151410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 14:10
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 15 March 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 15 March 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.