Filter by category
Filter by Date
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 1530 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024
Inter-regional transfer limit variation - Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024
A planned outage of Tungkillo-Tailem_Bnd 1 275kV LINE in the SA region was scheduled from 0845 hrs 16/07/2024 to 1630 hrs 16/07/2024.
The outage has been completed and Tungkillo-Tailem_Bnd 1 275kV LINE returned to service at 1255 hrs 16/07/2024
Constraint set(s) revoked: S-TBTU
Manager NEM Real Time Operations
CHG0090458 | Production | Planned Maintenance to Brisbane Internet firewall.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Change Start Date & Time: 20/07/2024 14:00:22 AEST
Change End Date & Time: 20/07/2024 17:00:22 AEST
Outage Start Date & Time: 20/07/2024 14:30:26 AEST
Outage End Date & Time: 20/07/2024 14:35:26 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Brisbane DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point prior to this scheduled outage.
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0091273 | Completed | Pre-Production | Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090717 | Cancelled | Production | NSW Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: NSW Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0090718 | Cancelled | Production | QLD Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: QLD Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024
Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024
A planned outage of Robertstown - Tungkillo No.1 275 kV line in the SA region was scheduled to be completed at 1730 hrs 14/07/2024.
The outage has been completed and Robertstown - Tungkillo No.1 275 kV line returned to service at 2043 hrs 12/07/2024
Constraint set(s) revoked: S-RBTU
Manager NEM Real Time Operations
CHG0091275 | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Change Start Date & Time: 21/07/2024 10:00:00 AEST
Change End Date & Time: 21/07/2024 14:00:00 AEST
Outage Start Date & Time: 21/07/2024 10:00:00 AEST
Outage End Date & Time: 21/07/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090719 | Cancelled | Production | Change to MarketNet SSL VPN
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: Change to MarketNet SSL VPN
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600