116437RESERVE NOTICE02/05/2024 03:27:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 0000 hrs to 0200 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1304 MW.


AEMO Operations
116436RESERVE NOTICE02/05/2024 03:29:37 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 0500 hrs to 0830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1265 MW.

From 1530 hrs to 2359 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1252 MW.


AEMO Operations

116435RESERVE NOTICE02/05/2024 03:28:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1700 hrs to 1800 hrs 07/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1355 MW.

AEMO Operations.
116433RESERVE NOTICE02/05/2024 01:49:57 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 02/05/2024 to 1830 hrs 02/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1390 MW.

Manager NEM Real Time Operations
116346INTER-REGIONAL TRANSFER27/04/2024 08:41:29 AM

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

At 0830 hrs 27/04/2024 there was a short notice outage of Dapto - Marulan No. 8 330 kV Line.

Constraint set(s) invoked: N-DTMN_8_15M

This constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116275INTER-REGIONAL TRANSFER23/04/2024 08:52:22 AM

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

At 0837 hrs 23/04/2024 there was an unplanned outage of Para No 1 SVC.

Constraint set(s) invoked: S-PA_VC1


This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116272INTER-REGIONAL TRANSFER22/04/2024 02:55:17 PM

Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.

The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024

Constraint set(s) revoked: N-LDTM_82_OPEN

Manager NEM Real Time Operations
116270INTER-REGIONAL TRANSFER22/04/2024 01:32:54 PM

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

At 1315 hrs 22/04/2024 there was an unplanned outage of Farrell - Sheffield Nos 1 and 2 220kV Lines.

The following constraint set(s) invoked at 1315 hrs 22/04/2024
T-X_FASH_C

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116209INTER-REGIONAL TRANSFER20/04/2024 12:10:41 AM

Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024

At 2341 hrs 19/04/2024 there was an unplanned outage of the Tailem Bend 275 kV Capacitor.

The following constraint set(s) invoked at 0005 hrs 20/04/2024
S-TBCP1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm