Market Notices

113858RESERVE NOTICE27/01/2024 02:47:55 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1530 hrs 29/01/2024 to 1600 hrs 29/01/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 1167 MW.

[2.] From 1630 hrs 29/01/2024 to 2030 hrs 29/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1068 MW.

Manager NEM Real Time Operations
113857RESERVE NOTICE27/01/2024 02:46:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1700 hrs 28/01/2024 to 2130 hrs 28/01/2024.
The forecast capacity reserve requirement is 1066 MW.
The minimum capacity reserve available is 977 MW.

Manager NEM Real Time Operations
113854RESERVE NOTICE27/01/2024 02:20:23 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113785 has been updated at 1400 hrs to the following:

[1.] From 1700 hrs 27/01/2024 to 1900 hrs 27/01/2024.
The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 583 MW.

[2.] From 1930 hrs 27/01/2024 to 2200 hrs 27/01/2024.
The forecast capacity reserve requirement is 1009 MW.
The minimum capacity reserve available is 540 MW.

Manager NEM Real Time Operations
113825POWER SYSTEM EVENTS27/01/2024 01:57:16 AM

Non-credible contingency event - QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/01/2024

At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
113785RESERVE NOTICE26/01/2024 03:52:21 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113769 has been updated at 1545 hrs to the following:

[1.] From 1630 hrs 27/01/2024 to 2200 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 607 MW.

Manager NEM Real Time Operations
113771RESERVE NOTICE26/01/2024 02:37:17 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113745 has been updated at 1435 hrs 26/01/2024 to the following:

[1.] From 1300 hrs 28/01/2024 to 1530 hrs 28/01/2024.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 801 MW.

Manager NEM Real Time Operations
113770RESERVE NOTICE26/01/2024 01:58:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113767 is cancelled at 1355 hrs 26/01/2024.

Manager NEM Real Time Operations
113769RESERVE NOTICE26/01/2024 02:26:34 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

[1.] From 1630 hrs 27/01/2024 to 1730 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 572 MW.

[2.] From 2030 hrs 27/01/2024 to 2100 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 621 MW.

[3.] From 2130 hrs 27/01/2024 to 2230 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 740 MW.

Manager NEM Real Time Operations
113767RESERVE NOTICE26/01/2024 01:00:21 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113765 has been updated at 1250 hrs to the following:

[1.] From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 1012 MW.

[2.] From 1630 hrs 27/01/2024 to 1700 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 840 MW.

[3.] From 2030 hrs 27/01/2024 to 2230 hrs 27/01/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 623 MW.

Manager NEM Real Time Operations