Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120468
The JLB02 JEERALANG B PO direction is now expected to stay in place until 0700 hrs 15/11/2024.
The direction update is issued at 0415 hrs 15/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120467
The JLB01 JEERALANG B PO direction is now expected to stay in place until 0700 hrs 15/11/2024.
The direction update is issued at 0415 hrs 15/11/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120465 is cancelled at 2320 hrs
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120464
The JLB02 JEERALANG B PO direction is now expected to stay in place until 0500 hrs 15/11/2024.
The direction update is issued at 2140 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120463
The JLB01 JEERALANG B PO direction is now expected to stay in place until 0500 hrs 15/11/2024.
The direction update is issued at 2140 hrs 14/11/2024.
Manager NEM Real Time Operations
[EventId:202411142125_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 November 2024 21:25
Issued by Australian Energy Market Operator Ltd at 2125 hrs on 14 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 November 2024.
Refer to market notice: 120451
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2125 hrs on 14 November 2024.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The forecast capacity reserve requirement is 1221 MW.
The minimum capacity reserve available is 1163 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120443
The JLB02 JEERALANG B PO direction is now expected to stay in place until 2300 hrs 14/11/2024.
The direction update is issued at 2015 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120442
The JLB01 JEERALANG B PO direction is now expected to stay in place until 2300 hrs 14/11/2024.
The direction update is issued at 2015 hrs 14/11/2024.
Manager NEM Real Time Operations