CHG0098812 | Completed | Pre-Production | Pre-Prod MSATS and eMDM November Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Market Settlement & Transfer System
Change Title: Pre-Prod MSATS and eMDM November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0098814 | Production | MSATS and eMDM November Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS and eMDM November Maintenance Release
Change Start Date & Time: 27/10/2024 10:00:00 AEST
Change End Date & Time: 27/10/2024 17:00:00 AEST
Outage Start Date & Time: 27/10/2024 10:00:00 AEST
Outage End Date & Time: 27/10/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Cancellation - MSL1- VIC Region at 1300 hrs 13/10/2024.
Cancellation - MSL1- VIC Region at 1300 hrs 13/10/2024.
Refer to Market Notice 11836 for MSL1.
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Update to Market Notice 118834 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs 13/10/2024 to 1330 hrs 13/10/2024.
Minimum regional demand is forecast to be 1265 MW at 1230 hrs, and the advisory threshold is:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.
Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.
Refer to Market Notice 118809 for MSL1.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.
Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.
Refer to Market Notice 118803 for MSL1.
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024
Update to Market Notice 118749 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1200 hrs 13/10/2024 to 1230 hrs 13/10/2024.
Minimum regional demand is [forecast to be] 1557 MW at 1230 hrs, and the advisory threshold is:
? MSL1 - 1560 MW
? MSL2 - 1010 MW
? MSL3 - 510 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the xxx threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 12/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1230 hrs 12/10/2024 to 1330 hrs 12/10/2024.
Minimum regional demand is forecast to be 1585 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1605 MW
o MSL2 - 1105 MW
o MSL3 - 605 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
AEMO Operations