[EventId:202402131320_confirmed] Prices for interval 13-Feb-2024 13:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1452 hrs on 14 February 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2024 13:20.
In accordance with Market Notice 114583 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 -$38.41 -$35.04
QLD1 -$40.60 -$36.57
LOWERREG
TAS1 $16,600.00 $9.88
RAISEREG
TAS1 $16,600.00 $150.68
This is an AEMO autogenerated Market Notice.
Update: Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024
At 1827 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region, the following plant was returned to service.
The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer
The Jeeralang - Hazelwood No 2 220kV line remains out of service.
Refer to Network outage scheduler (NOS) for further details.
Refer Market notice 114641 and 114643
This Market Notice is issued in accordance with NER clause 4.8.3.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.
Manager NEM Real Time Operations
Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024
At 1543 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region the following plant tripped.
The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer
The Jeeralang Hazelwood No2 220kV line.
Refer Market notice 114641
Updates will be provided as additional information becomes available.
This Market Notice is issued in accordance with NER clause 4.8.3.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 13/02/2024
Non-credible contingency event - TAS region - 13/02/2024
At 1602 hrs the Norwood -Scottsdale 110kV line and the Norwood - Scottsdale -Derby 110kV line tripped.
AEMO did not instruct load shedding.
AEMO has been advised 8MW of electrical load and 24MW of generation has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Significant power system event - Victoria region - 13/02/2024
At 1308 hrs 13/02/2024 the Moorabool Sydenham No1 and No2 500 kV lines tripped.
There have been reports of towers on the ground.
In the Victorian region
1000 MW of customer load lost during the fault has been restored
2690 Generation tripped
The AEMO instructed loadshed of 300 MW is being progressively restored.
Updates will be provided as additional information becomes available.
This Market Notice is issued in accordance with NER clause 4.8.3.
Manager NEM Real Time Operations
Significant power system event - 13 Feb 2024
Significant power system event - 13 Feb 2024
At 1308 hrs 13/02/2024 a significant power system event occurred.
Description of event - Multiple tripping of generation and transmission lines in the Vic region
Transmission element(s) tripped - Moorabool Sydenham No1 and No2 500 kV lines tripped
Region/s - Vic
Load interrupted - in excess of 1000 MW
Generation volume tripped - 2300 MW
Updates will be provided as additional information becomes available.
This Market Notice is issued in accordance with NER clause 4.8.3.
Manager NEM Real Time Operations
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Refer AEMO Electricity Market Notice 113825
At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.
AEMO has received further information and now determines this was not a non-credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 27/01/2024
Non-credible contingency event - QLD region - 27/01/2024
At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations