[EventId:202412051305_review] Prices for interval 05-Dec-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update to system strength requirements in North Queensland
Refer to market notice 106175
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.
A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF
Two new equations have been added:
-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 03/12/2024 to 1830 hrs 03/12/2024.
The forecast capacity reserve requirement is 1573 MW.
The minimum capacity reserve available is 1541 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121414 is cancelled at 1415 hrs 03/12/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121406 is cancelled at 1215 hrs 03/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03 Dec 2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121405 has been updated at 1115 hrs to the following:
[1.] From 1330 hrs 03/12/2024 to 1600 hrs 03/12/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 1081 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 03 Dec 2024
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 121386 has been updated at 0750 hrs to the following:
[1.] From 1800 hrs 03/12/2024 to 1930 hrs 03/12/2024.
The forecast capacity reserve requirement is 1127 MW.
The minimum capacity reserve available is 991 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03 Dec 2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121392 has been updated at 0750hrs to the following:
[1.] From 1200 hrs 03/12/2024 to 1400 hrs 03/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1129 MW.
[2.] From 1430 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1326 MW.
Manager NEM Real Time Operations
[EventId:202412030705_review] Prices for interval 03-Dec-2024 07:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 3 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 03-Dec-2024 07:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs