RESERVE NOTICE MT PASA PUBLICATION 06 February 2024
-- February 2025 - February 2026 in New South Wales.
AEMO declares low reserve conditions in accordance with clause 4.8.4 of the National Electricity Rules for the following region(s) and periods:
-- February 2025 - February 2025
-- August 2025 - February 2026
in New South Wales when forecast demand exceeds supply under some circumstances.
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 114005 published on 30 January 2024.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National
Forecasting
AEMO
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114284 has been updated at 1115hrs to the following:
[1.] From 1400 hrs 05/02/2024 to 1530 hrs 05/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 814 MW.
[2.] From 1700 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 750 MW.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 05/02/2024 11:20 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114283 has been updated at 1115 hrs to the following:
[1.] From 1530 hrs 05/02/2024 to 1700 hrs 05/02/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 652 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1400 hrs on 05/02/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.114270 has been updated at 1015 hrs to the following:
[1.] From 1800 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 865 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114279 has been updated at 2350 hrs to the following:
[1.] From 1330 hrs 05/02/2024 to 1500 hrs 05/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 759 MW.
[2.] From 1800 hrs 05/02/2024 to 1930 hrs 05/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 851 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114278 has been updated at 0945 hrs to the following:
[1.] From 1500 hrs 05/02/2024 to 1800 hrs 05/02/2024.
The forecast capacity reserve requirement is 734 MW.
The minimum capacity reserve available is 467 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs on 05/02/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 5 February 2024
NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SEBSF1
Duration: 04/02/2024 12:45 to 05/02/2024 09:40
Amount: 35 MW
Constraint: NC-N_SEBSF1
Auto-generated on behalf of Manager NEM Real Time Operations