Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113674 is cancelled at 1400 hrs 24/01/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.113673 has been updated at 1400 hrs 24/01/2024 to the following:
[1.] From 1630 hrs 27/01/2024 to 1800 hrs 27/01/2024.
The forecast capacity reserve requirement is 1231 MW.
The minimum capacity reserve available is 714 MW.
[2.] From 2000 hrs 27/01/2024 to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 1191 MW.
The minimum capacity reserve available is 763 MW.
[3.] From 2200 hrs 27/01/2024 to 2300 hrs 27/01/2024.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 830 MW.
AEMO Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 113695
The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 25/01/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 24/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.113670 has been updated at 1400 hrs 24/01/2024 to the following:
[1.] From 1730 hrs 26/01/2024 to 1830 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1398 MW.
[2.] From 2000 hrs 26/01/2024 to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1429 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113685 has been updated at 1300 hrs 24/01/2024 to the following:
From 1830 hrs 26/01/2024 to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 1326 MW.
The minimum capacity reserve available is 730 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1500 hrs 25/01/2024 to 1530 hrs 25/01/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1349 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1530 hrs 25/01/2024 to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1229 MW.
The minimum capacity reserve available is 838 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 26/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113686 has been updated at 1200 hrs 24/01/2024 to the following:
From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 724 MW.
The minimum capacity reserve available is 504 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations