113538RESERVE NOTICE20/01/2024 03:01:21 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1830 hrs 21/01/2024 to 1900 hrs 21/01/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1253 MW.


Manager NEM Real Time Operations
113532RESERVE NOTICE20/01/2024 02:37:35 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1232 MW.
The minimum capacity reserve available is 1124 MW.


Manager NEM Real Time Operations
113531RESERVE NOTICE20/01/2024 02:31:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113477 has been updated at 1430 hrs 20/01/2024 to the following:

[1.] From 1830 hrs 25/01/2024 to 1930 hrs 25/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1111 MW.

Manager NEM RTO
113530RESERVE NOTICE20/01/2024 02:29:02 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113479 has been updated at 1430 hrs 20/01/2024 to the following:

[1.] From 1500 hrs 25/01/2024 to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 965 MW.

Manager NEM RTO
113527RESERVE NOTICE20/01/2024 01:25:55 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 21/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 21/01/2024 to 1900 hrs 21/01/2024.
The forecast capacity reserve requirement is 1249 MW.
The minimum capacity reserve available is 1082 MW.


Manager NEM Real Time Operations
113522RESERVE NOTICE19/01/2024 08:27:14 PM

Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113498 is cancelled at 2000 hrs 19/01/2024.

Manager NEM Real Time Operations
113498RESERVE NOTICE19/01/2024 05:44:26 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 982 MW
The minimum capacity reserve available is 938 MW

Manager NEM Real Time Operations
113479RESERVE NOTICE19/01/2024 03:29:01 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113410 has been updated at 1400 hrs 19/01/2024 to the following:

From 1900 hrs to 1930 hrs 25/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1258 MW.

AEMO Operations
113477RESERVE NOTICE19/01/2024 03:28:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1118 MW.