116642RESERVE NOTICE17/05/2024 11:21:55 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116641 has been updated at 1000 hrs 17/05/2024 to the following:

From 0600 hrs 20/05/2024 to 0830 hrs 20/05/2024.
The forecast capacity reserve requirement is 1240 MW.
The minimum capacity reserve available is 868 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
116641RESERVE NOTICE17/05/2024 08:56:09 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0600 hrs to 0730 hrs 20/05/2024.
The forecast capacity reserve requirement is 1126 MW.
The minimum capacity reserve available is 1121 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
116639SETTLEMENTS RESIDUE16/05/2024 05:45:28 PM

[EventId:202405161745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 May 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.

Refer to market notice: 116637

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 16 May 2024.

This is an AEMO autogenerated Market Notice.
116637SETTLEMENTS RESIDUE16/05/2024 05:30:33 PM

[EventId:202405161730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 May 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 16 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
116551SETTLEMENTS RESIDUE08/05/2024 08:30:22 PM

[EventId:202405082030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 20:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2030 hrs on 8 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Refer to market notice: 116542

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 8 May 2024.

This is an AEMO autogenerated Market Notice.
116549RESERVE NOTICE08/05/2024 07:22:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116545RESERVE NOTICE08/05/2024 05:19:39 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
116542SETTLEMENTS RESIDUE08/05/2024 03:30:23 PM

[EventId:202405081530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 8 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 8 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
116524SETTLEMENTS RESIDUE08/05/2024 08:30:23 AM

[EventId:202405080830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 08:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 8 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Refer to market notice: 116521

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0830 hrs on 8 May 2024.

This is an AEMO autogenerated Market Notice.