Filter by category
Filter by Date
[EventId:202312151000_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2023 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 15 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1000 hrs on 15 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.
Manager NEM Real Time Operations
[EventId:202312141900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 December 2023 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 14 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Refer to market notice: 112347
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 14 December 2023.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW
Manager NEM Real Time Operations
[EventId:202312141600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 December 2023 16:00
Issued by Australian Energy Market Operator Ltd at 1601 hrs on 14 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 14 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312141530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 December 2023 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 14 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Refer to market notice: 112322
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 14 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312141400_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 December 2023 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 14 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1400 hrs on 14 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312141330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 December 2023 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 14 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Refer to market notice: 112315
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 14 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312141130_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 December 2023 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 14 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1130 hrs on 14 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.