Market Notices

112803GENERAL NOTICE27/12/2023 10:08:01 AM

Update - Lightning vulnerable lines in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in QLD region

Refer to AEMO Electricity Market Notice 112794

At 2345 hrs 26/12/2023, the Clare South - Strathmore No.7208 and Strathmore - Clare South tee King Creek No.7128 132 kV Lines tripped.

The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Clare South - Strathmore No.7208 and Strathmore - Clare South tee King Creek No.7128 132 kV Lines to be vulnerable with a category of "Probable" due to Lightning.

Manager NEM Real Time Operations
112662SETTLEMENTS RESIDUE24/12/2023 01:00:19 PM

[EventId:202312241300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 December 2023 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 24 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.

Refer to market notice: 112657

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 24 December 2023.

This is an AEMO autogenerated Market Notice.
112657SETTLEMENTS RESIDUE24/12/2023 11:31:35 AM

[EventId:202312241130_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 December 2023 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1130 hrs on 24 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112653SETTLEMENTS RESIDUE24/12/2023 10:30:29 AM

[EventId:202312241030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 December 2023 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 24 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.

Refer to market notice: 112652

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1030 hrs on 24 December 2023.

This is an AEMO autogenerated Market Notice.
112652SETTLEMENTS RESIDUE24/12/2023 09:05:25 AM

[EventId:202312240905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 December 2023 09:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0905 hrs on 24 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 24 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112589SETTLEMENTS RESIDUE22/12/2023 10:00:27 AM

[EventId:202312221000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2023 10:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 22 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2023.

Refer to market notice: 112588

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 22 December 2023.

This is an AEMO autogenerated Market Notice.
112588SETTLEMENTS RESIDUE22/12/2023 09:00:24 AM

[EventId:202312220900_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2023 09:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 22 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0900 hrs on 22 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112580SETTLEMENTS RESIDUE21/12/2023 03:05:24 PM

[EventId:202312211505_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 21 December 2023 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 21 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2023.

Refer to market notice: 112577

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1505 hrs on 21 December 2023.

This is an AEMO autogenerated Market Notice.
112577SETTLEMENTS RESIDUE21/12/2023 02:01:05 PM

[EventId:202312211400_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 21 December 2023 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 21 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1400 hrs on 21 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.