Direction - SA region 06/12/2024
Direction - SA region 06/12/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1620 hrs on 06/12/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Foreseeable AEMO intervention in SA region
Foreseeable AEMO intervention in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 07/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1615 hrs 06/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 6 December 2024
NON-CONFORMANCE NSW1 Region Friday, 6 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 4 December 2024
NON-CONFORMANCE VIC1 Region Wednesday, 4 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNB1
Duration: 04/12/2024 20:55 to 04/12/2024 21:05
Amount: -24 MW
Constraint: NC-V_GANNB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 4 December 2024
NON-CONFORMANCE NSW1 Region Wednesday, 4 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 04/12/2024 06:25 to 04/12/2024 06:40
Amount: -16 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 3 December 2024
NON-CONFORMANCE NSW1 Region Tuesday, 3 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 03/12/2024 11:05 to 03/12/2024 11:15
Amount: -58 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 3/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice121410 is cancelled at1055 hrs 3/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 3/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121407 has been updated at 1015 hrs to the following:
[1.] From 1330 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 461 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 03/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1330 hrs 03/12/2024 to 1400 hrs 03/12/2024.
The forecast capacity reserve requirement is 771 MW.
The minimum capacity reserve available is 741 MW.
[2.] From 1430 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 809 MW.
The minimum capacity reserve available is 636 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.