Market Notices

120481MARKET INTERVENTION15/11/2024 04:27:40 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120432

Direction is cancelled from: 1630 hrs 15/11/2024

Manager NEM Real Time Operations
     
120480MARKET INTERVENTION15/11/2024 02:25:54 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120444

Direction is cancelled from: 1430 hrs 15/11/2024

Manager NEM Real Time Operations
     
120479NON-CONFORMANCE15/11/2024 11:15:16 AM

NON-CONFORMANCE Region NSW1 Friday, 15 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 15 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 15/11/2024 11:00 to 15/11/2024 11:15
Amount: -7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120477MARKET INTERVENTION15/11/2024 07:58:55 AM

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

Refer to Market Notice 120473

Direction is cancelled from: 0800 hrs 15/11/2024

Manager NEM Real Time Operations
     
120476MARKET INTERVENTION15/11/2024 06:53:13 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 15/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
120475MARKET INTERVENTION15/11/2024 06:39:22 AM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120472

The JLB02 JEERALANG B PO direction is now expected to stay in place until 0900 hrs 15/11/2024.

The direction update is issued at 0645 hrs 15/11/2024.

Manager NEM Real Time Operations
     
120474MARKET INTERVENTION15/11/2024 06:38:08 AM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120471

The JLB01 JEERALANG B PO direction is now expected to stay in place until 0900 hrs 15/11/2024.

The direction update is issued at 0645 hrs 15/11/2024.

Manager NEM Real Time Operations
     
120473MARKET INTERVENTION15/11/2024 06:27:02 AM

Direction - VIC region to Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Direction - VIC region to Snowy Hydro Limited - MURR2-2 MURRAY2

Refer to Market Notice 120404


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Snowy Hydro Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2 at 0630 hrs 15/11/2024
Type of resource: generating unit operating as synchronous condenser
Required actions: Remain synchronised and operate as a synchronous condenser at 0630 hrs 15/11/2024
Services provided: System Strength
Circumstances necessitating the Direction:System Strength
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0900 hrs 15/11/2024.

Snowy Hydro Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120472MARKET INTERVENTION15/11/2024 04:18:33 AM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120468

The JLB02 JEERALANG B PO direction is now expected to stay in place until 0700 hrs 15/11/2024.

The direction update is issued at 0415 hrs 15/11/2024.

Manager NEM Real Time Operations
     