Market Notices

120591RESERVE NOTICE18/11/2024 05:24:42 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120587 is cancelled at 0515 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120587RESERVE NOTICE17/11/2024 11:58:20 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1830 hrs 18/11/2024 to 1900 hrs 18/11/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 1415 MW.

Manager NEM Real Time Operations
     
120581SETTLEMENTS RESIDUE17/11/2024 08:35:27 PM

[EventId:202411172035_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 November 2024 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 17 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.

Refer to market notice: 120561

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2035 hrs on 17 November 2024.

This is an AEMO autogenerated Market Notice.
     
120580RESERVE NOTICE17/11/2024 07:54:00 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120576 is cancelled at 1945 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120578RESERVE NOTICE17/11/2024 07:55:09 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120574 is cancelled at 1945 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120576RESERVE NOTICE17/11/2024 07:15:32 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120573 has been updated at 1915 hrs to the following:

[1.] From 1800 hrs 18/11/2024 to 2000 hrs 18/11/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 814 MW.


Manager NEM Real Time Operations
     
120574RESERVE NOTICE17/11/2024 05:12:18 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120547 to the following period:

[1.] From 1800 hrs 18/11/2024 to 1930 hrs 18/11/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 1082 MW.

Manager NEM Real Time Operations
     
120573RESERVE NOTICE17/11/2024 05:07:42 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120549 to the following period:

[1.] From 1800 hrs 18/11/2024 to 1930 hrs 18/11/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 1013 MW.


Manager NEM Real Time Operations
     
120563PRICES SUBJECT TO REVIEW17/11/2024 04:10:15 PM

[EventId:202411171615_review] Prices for interval 17-Nov-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 17 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Nov-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm